September 28, 2018

Managed to get the piles in as well as all of the footings for the first building.

September 25, 2018

Despite some snowflakes (while it was technically still summer) we managed to get the first town home building dug out.  

September 20, 2018

Despite the rain, the first town home building has been staked and is ready to be dug.

September 18, 2018

The water and sewer lines are in throughout our site.  Fire hydrants and man holes are a visible indicator of all the work done by DC Trenching.  These photos are proof of the hard work they put in.  

September 13, 2018

Our office and sales centre is now open at 309 Main Street in Hague, SK.  Come visit us soon!

Please reload

Our Recent Posts

July 12, 2019

June 19, 2019

Please reload

Archive

Please reload

Tags

I'm busy working on my blog posts. Watch this space!

Please reload

 

Address

Claystone Developments
309 Main Street, Box 238
Hague, SK  S0K 1X0 
Canada

Contact

Follow

(306) 700-3130

©2019 by Claystone Developments Ltd.